Latest updated for IATL buidling
-
August 21, 2008 - Currently we are still being told that Oct 1, 2008 is occupation date for the 2nd, 3rd and 4th floors.
-
August 18 - There is now power to the 3rd floor labs.
-
August 13 - There is no power to the 3rd floor labs. Jill is checking into this.
-
August 5, 2008 - As of today they will be letting IATL occupants into the building to start assessing equipment and to remove stuff from their offices/labs. Compressed air is working to all labs, as well as electrical.